SilverCrest Metals reports first pour at Las Chispas mine

SilverCrest Metals records 9,200oz of silver and 100oz of gold in first pour at Las Chispas mine in Mexico

SilverCrest Metals has reported first silver and gold pour at its Las Chispas mine in Sonora, Mexico.

The first precious metal pour was completed on June 30, and consisted of 312kg of dore with approximately 9,200oz of silver and 100oz of gold.

CEO N. Eric Fier said it marked another significant milestone in progressing towards commercial production in Q4.

COO Pierre Beaudoin was pleased with the initial trajectory of the plant commissioning.

"While it is still early days in the plant ramp-up, we are encouraged by some of the operating indicators," he said.

"Underground mining rates and our knowledge of the deposit continue to increase."

Key data, plant performance and an updated technical report, including resources, reserves, mine plan, revised costs and economics, are expected to be released in H1, 2023.

Underground mining rates have increased during the quarter with production from stoping and in-vein development in a number of veins. Mining is active using two mining methods.

As outlined in the company’s Feasibility Study, the processing plant is expected to utilise low-grade historic stockpiles through the ramp-up, reducing the reliance on underground mine production at the start of the operation. 

SilverCrest targets 1,250 tonnes per day at Las Chispas mine

Overall, the plant commissioning is tracking in-line with SilverCrest's objective to reach nameplate capacity of 1,250 tonnes per day.

The plant, which started late May, milled an estimated 12,700 tonnes of low-grade ore during June. Metallurgical recoveries are expected to reach Feasibility Study parameters in 2023 and results observed to date are tracking toward these objectives.

During Q1, Las Chispas expenditures recorded under mineral property, plant and equipment totaled $21.4mn (inclusive of unpaid accrued expenditures), of which $1.2mn was for plant and equipment purchases, $6.1mn for construction in progress costs, and $14.1mn for mineral property costs.

To the end of Q1, it committed $114.6mn (83.2%) of the $137.7mn Feasibility Study capital cost estimate and incurred $108mn.

Of the remaining capital budget to be incurred in Q2 ($29.7mn), 22% ($6.3mn) is related to the Ausenco fixed price EPC contract for process plant construction and 27% ($8mn) is unused contingency.

SilverCrest completed 2km of underground development in the quarter, for a total of 19.5km of underground development since 2019.

The company expects to provide further updates on the commissioning and ramp-up of operations in Q3.

Share

Featured Articles

2024 Olympic Medals: All That Glitters is Not Gold

Iron from the Eiffel Tower is a signature part of all the medals at the 2024 Paris Games, and the tale of the iron's origins reads like a detective novel

UK Coal Mine Legal Battle puts Sustainability in Spotlight

UK’s first new deep coal mine in 30 years faces legal challenge, putting the world's complicated relationship with this fossil fuel into the spotlight

Rio Tinto Brings Simandou Guinea Iron Ore Saga to End

Rio Tinto ready to resume construction at Simandou mine in Guinea, which be world's largest iron ore operation and Africa's biggest infrastructure project

Focus on: Uranium, the World's Most Powerful Metal

Supply Chain & Operations

Why Nickel Price Slump has hit BHP so Hard

Supply Chain & Operations

Worley: Tech Key for Copper Ramp-up to be Sustainable

Operations